A newly filed Texas bill could involve annual payments to residents.
The bill, filed on November 20 by Democratic state representative-elect Cecilia Castellano, was covered by Click2Houston, whose headline suggested it could lead to yearly payments for residents.
Eligibility Terms in a Separate Proposal
The Texas Dispatch describes SB 296 as including similar residency and eligibility terms.
Scope and Permitting in a Separate Proposal
The Texas Dispatch describes SB 296 as covering computing, AI training and storage, and requiring a state environmental permit supported by studies.
The Texas Dispatch gives SB 296 an effective date of September 1, 2027, unless two-thirds of the elected members of each legislative chamber vote for immediate effect.
Part of a Broader Pushback on Data Centers
Castellano's bill isn't Texas's only attempt to rein in data center growth. The Texas Dispatch reports that a separate proposal, Senate Bill 296, would pause approvals and utility hookups for certain new or expanded data centers for two years, after which a facility would need both local voter approval and a state environmental permit. The Texas Dispatch also notes that other lawmakers have taken narrower approaches — House Bill 928 would require a commissioners court vote, while Senate Bills 32 through 36 would let counties establish data-center districts and require a state utility commission permit.
The push for more local control comes as data centers draw growing resistance nationwide. Stateline reported that voters passed 44 ballot measures restricting data centers this election cycle, with two more holding significant leads in ongoing vote counts, and those measures ranged from outright prohibitions to temporary moratoriums, energy-use limits, and voter-approval mandates. According to Stateline, residents in 21 Ohio municipalities alone have turned to local ballot measures or referendums to try to stop proposed data centers, and a UMass Amherst poll it cited found just 11% of Americans would support building an AI data center in their own community.
The Grid Pressure Driving the Debate
The resistance tracks with surging demand on the Texas grid. ERCOT's preliminary long-term forecast projects roughly 367,790 megawatts of demand across its region by 2032, though the grid operator cautions that the figure is a planning snapshot rather than a prediction of what will actually get built, according to ERCOT.
Whether HB 1273 or any of the competing Texas proposals will advance, and whether they would apply to specific projects already in the pipeline, remains to be seen as the legislature takes up the issue.