Construction crews are laying concrete and asphalt this month at Metro Bus's new transit hub taking shape at 441 Second Avenue South in Waite Park, with the agency now eyeing an opening sometime in the second or third quarter of 2027. The project's structural frame is already up, according to Metro Bus Chief Operating Officer Dave Green, and workers are racing to finish outdoor work before winter sets in for good.
The facility marks Metro Bus's second transit hub and is meant to complement its existing transit center downtown, according to WJON. Metro Bus finalized its purchase of two parcels of land at the Waite Park site back in January 2024, laying the groundwork for a project that a 2019 feasibility study and a long-range transit plan update had identified as a need for improving service in the western part of the agency's coverage area, according to Finance & Commerce.
Frame Up, Dirt Work Behind Them
The pace of work has shifted noticeably since earlier this year. An earlier WJON update on the project described most of the activity at the site as simply moving dirt, but the station's more recent report notes the transit-structure frame is now built and crews are laying concrete and asphalt as of this month, per Green. Construction teams are prioritizing outdoor portions of the project before cold and wintry weather arrives, with interior work planned to continue through the winter months, Green said.
Metro Bus officially kicked off construction on the facility alongside project partners, according to a groundbreaking announcement posted on the agency's website. The agency selected Oertel Architects to design and build the Western Transit Center, with the Metro Bus Board of Commissioners approving that selection on May 20, the same announcement notes.
Opening Timeline Has Shifted
Exactly when the hub will welcome riders has moved around in Metro Bus's own public statements. The agency's architect-selection announcement had described the facility as tentatively scheduled to open in late 2026 alongside the rollout of Metro Bus Forward service changes. More recently, the agency's groundbreaking announcement said it anticipates completing the new facility in 2027, with timing for a grand opening and the Metro Bus Forward changes still to be announced — language that echoes Finance & Commerce's reporting that the hub is expected to open in 2027 with a grand-opening date yet to be determined. Green told WJON the agency would like to open the facility as early as mid-summer 2027, and in the station's more recent report, he pegged the opening window to the second or third quarter of that year, with the opening planned to align with the service changes.
Once finished, the hub is expected to provide greater route and service flexibility and improve the overall experience for riders, Green said. Metro Bus Forward includes proposed route realignments, extensions and service-frequency changes, according to St. Cloud Live, and current plans call for as many as 16 buses per hour to operate out of the new hub, per Finance & Commerce. Waite Park Mayor Ken Schmitt said the project would improve accessibility and connectivity for residents, shorten travel times, improve service to underserved areas and strengthen regional connections, according to Finance & Commerce's reporting.
What's Inside the New Building
Plans for the site call for a transit center building with office space, a waiting area, a break room, restrooms and flex space, along with landscaping and other site improvements, according to a bid advertisement from the St. Cloud Metropolitan Transit Commission. The project is designed to work alongside Metro Bus's existing downtown transit center rather than replace it, supporting the broader system as new routes and services come online under Metro Bus Forward.
The construction progress comes as Metro Bus points to ridership gains systemwide. Green said ridership has climbed steadily since a pandemic-related downturn in 2020, including a 7% increase compared with the previous year, and he pointed to the agency's growing paratransit dial-a-ride service as another area of expansion. Metro Bus has not announced a finalized grand-opening date for the Waite Park facility or a final schedule for the Metro Bus Forward service changes.