Fisher Street in Westborough could soon get a dedicated walking and biking path, pavement rehabilitation, and other upgrades under a state proposal aimed at making the corridor safer for kids walking to school. Massachusetts state transportation officials will hold a public hearing on the proposed improvements Wednesday, Dec. 9, giving residents an opportunity to weigh in on the design.
The Massachusetts Department of Transportation project would cover Fisher Street from Eagle Scout Trail to Church Street, improving connections to Sarah W. Gibbons Middle School and Armstrong Elementary School, according to Patch. Gibbons Middle School sits just off Fisher Street, and the broader goal of the project is to provide safer walking and bicycling connections to both nearby schools. As Community Advocate reports, a MassDOT hearing handout describing current conditions along the corridor points to broken and uneven sidewalks, insufficient curbing, and no dedicated bicycle accommodations.
What the Design Calls For
Plans call for an 8-foot-wide shared-use path along the south side of Fisher Street for pedestrians and bicyclists, per the same Patch report. The proposed roadway would generally feature 10.5-foot travel lanes with 2-foot shoulders, and the project would also include pavement rehabilitation and reconstruction, new granite curbing, accessible ADA-compliant curb ramps, pavement markings, signs and traffic-calming measures.
MassDOT's project page lists the work at 25% design. Construction itself is estimated to cost approximately $3.7 million. The project is programmed for federal fiscal year 2029 and is included in the Central Massachusetts Metropolitan Planning Organization's Transportation Improvement Program, a five-year regional spending plan updated annually that identifies transportation projects, estimated costs, and scheduled federal and state funding.
Easements and Property Rights
The project is expected to require temporary construction easements along the corridor as well as utility easements for several properties, and Westborough would be responsible for securing the necessary property rights, the town's report notes. During construction, crews would work to maintain access for residents and businesses, though temporary lane closures, alternating traffic, and pedestrian detours may be required at times. MassDOT officials are expected to explain the agency's land-acquisition policies during the upcoming hearing.
How to Weigh In
MassDOT will present the project during a design public hearing from 6:30 to 7:30 p.m. Wednesday, Dec. 9, at Great Hall in the Forbes Municipal Building, 45 West Main St., according to Patch. Attendees will be able to review plans, ask questions, and offer comments on the proposal in person. Those who want their comments included in the official hearing transcript must email or postmark written submissions within 10 business days after the hearing, referencing project 613367, and can send them to [email protected]. MassDOT has said it will review the feedback as the design advances.
Part of a Broader Safe Routes to School Push
The town and Gibbons and Armstrong Schools jointly applied for a MassDOT Safe Routes to School Infrastructure grant for the Fisher Street path, Patch reported separately. The push fits into a wider statewide effort: MassDOT has announced $13 million in infrastructure funding for eight communities, including three in western Massachusetts, through its Safe Routes to School Infrastructure Program, according to WWLP. That program has historically funded design and construction services for projects costing between $300,000 and $2 million, and nearby Holliston separately proposed a shared-use path and crosswalk along Linden Street under the same initiative, per WWLP's reporting.