Lehigh Valley/ Politics & Govt

Whitehall Township Locks In Data Center Rules With Unanimous 7-0 Vote

AI Assisted Icon
Published on November 18, 2026
Whitehall Township Locks In Data Center Rules With Unanimous 7-0 Vote3219 MacArthur Rd. — Township That Adopted Data Center Rules
Google Street View

Whitehall Township's Board of Commissioners voted 7-0 on Nov. 9 to approve a new zoning ordinance governing data centers, adding hyperscale data center terms and criteria to the township code after months of public debate over where such facilities could be built.

The vote caps a process that began with a first hearing in August, when commissioners heard from residents who voiced fears and concerns about a data center facility locating in or near the township, according to Lehigh Valley Press. At that Aug. 10 meeting, the board received public comment on the proposed rules but did not take a vote, per WFMZ.

The newly adopted ordinance defines artificial intelligence, cryptocurrency mining, data center, data center accessory use and hyperscale data center within the zoning code, according to the Lehigh Valley Press report. Data center uses must avoid detrimental impacts to high-value streams, wetlands, floodplains, steep slopes and other environmentally sensitive areas, and the uses are prohibited outright on prime agricultural soils, the Lehigh Valley Press reports.

Environmental Guardrails Built Into the Code

Beyond the agricultural and waterway protections, data center uses must minimize disturbances to natural and unimproved land, and the ordinance encourages preservation of mature trees and woodland areas, per the Lehigh Valley Press account. Developers must also meet project requirements that include water requirements and sound studies before building.

Those requirements echo what The Morning Call described in August, when the township's proposed ordinance would have required developers to submit studies on water use, noise levels and environmental impact. That earlier reporting also noted the draft rules would restrict data centers to specific industrial zones and bar them from prime agricultural soils and environmentally sensitive areas — language that tracks closely with what commissioners ultimately adopted.

Planning Boards Backed the Measure

Both the Whitehall Township Planning Commission and the Lehigh Valley Planning Commission recommended approval of the ordinance, according to the Lehigh Valley Press, citing township officials. Commissioner Taylor Stakes thanked Bureau Chief Lee Rackus and Township Solicitor Jack Gross for developing the ordinance, saying it will provide protections and regulations for the township and its citizens. Stakes also said the ordinance stands as strong protection against data center harms, while acknowledging it may need future updates as conditions change, the Lehigh Valley Press reports.

Whitehall is not alone in rewriting its zoning code for the data center boom. WFMZ reported that South Whitehall, North Whitehall, Upper Macungie, Lower Macungie and Lowhill townships have also recently updated their own data center ordinances, part of a broader scramble across the Lehigh Valley to get ahead of large-scale development proposals.

Bigger Fights Playing Out Nearby

The stakes of that scramble are visible just up the road in Upper Mount Bethel Township, where two proposed data center campus designs cover more than 900 acres spread on both sides of River Road, according to The Morning Call. One design includes 29 data center buildings totaling 3.5 million square feet, while the other includes six buildings totaling nearly 1.5 million square feet, the newspaper reports. Both designs list electrical demand at 2.1 gigawatts, a figure that has left regional planners confused about the project's total scope, and Lehigh Valley Planning Commission reviewers have asked for further information on necessary electrical infrastructure upgrades, per the same account.

Resistance has also surfaced in Northampton County, where more than 200 people packed an Aug. 17 public hearing in Lower Mount Bethel Township over a proposed ordinance establishing zoning and performance standards for data centers, according to The Center Square. Most speakers at that hearing urged supervisors to reject or strengthen the measure, the outlet reported, and a later revision of the Lower Mount Bethel Technology Center plan removed roughly 350 acres of agricultural land near Gravel Hill Road from the project footprint.

For now, Whitehall's commissioners have their framework in place, built around the same core concerns — farmland, waterways, noise and water use — that have animated debates across the region. Whether the ordinance holds up as actual proposals come forward remains to be seen, but Stakes has already signaled that commissioners expect to revisit the rules as conditions change.