Developer MAS Ventures LLC and Malek Abdulsamad marked a major construction milestone this week, celebrating the topping out of Lawrence Gateway, a five-story mixed-use building rising across from Ronan Park in Albany Park. Chicago's Department of Planning and Development Commissioner Ciere Boatright joined the celebration, underscoring the city's stake in a project that pairs market-rate apartments with affordable housing and ground-floor retail.
According to Urbanize Chicago, the building sits at 2923 W. Lawrence on a trapezoidal parcel that previously held a surface parking lot and a one-story masonry building. Designed by Wight & Company, the structure will reach 61 feet across five stories. Earlier project coverage and a notice from the 40th Ward's office had identified the site as 2919 W. Lawrence, where the ward said it had no objection to a zoning change from C1-2 to B3-3, according to the 40th Ward of Chicago.
Unit Mix and Affordability Details
The topping-out report describes 40 residential units in all — seven studios, 15 one-bedrooms and 18 two-bedrooms — with a quarter of them set aside as affordable, backed by a $5 million grant from the city's planning department. A later report from Chicago YIMBY offered a different tally, describing the property as having 41 units after a permit revision reportedly bumped the count up from 40, and putting the number of affordable apartments at eight rather than a straight 25 percent share, per the outlet's Chicago YIMBY coverage from April. The two accounts don't fully reconcile, and which figures reflect the final approved plans remains unclear.
Ground-floor space is planned for two retail bays with the residential entrance tucked between them. The topping-out article puts that retail area at roughly 9,300 square feet, while Chicago YIMBY's earlier reporting had described closer to 7,600 square feet of ground-floor retail. Residents, meanwhile, are promised a fifth-floor lounge and outdoor deck with views stretching north toward Ronan Park and the Chicago River.
Design Touches and Sustainability Goals
The facade is planned with corrugated metal panels, light bronze siding over the floor slabs and black window frames, while the retail podium below gets darker bronze metal paneling. A glass-clad central staircase with a mural on the front facade is also part of the design, the same Urbanize Chicago report notes.
Lawrence Gateway is designed to meet the city's sustainability requirements and to pursue Energy Star certification and the Zero Energy Ready Homes standard, though those remain goals rather than confirmed certifications at this stage. The building is planned to be all-electric, with no gas cooking or heating, relying instead on a VRF heating system, and it's designed to be solar-ready, per the same account.
Parking, Easements and a New Streetscape
A surface lot on the site's western side is planned to include 19 parking spaces, the topping-out report states, with two reserved for accessible parking and two for electric-vehicle charging. Block Club Chicago's earlier reporting on the approved plans described a somewhat different parking layout, citing 20 total spaces and four EV charging spots rather than two, according to Block Club Chicago. Chicago YIMBY's spring report cited yet another figure, 19 car spaces alongside parking for 41 bicycles. The topping-out article separately describes an indoor bike room with space for 40 bicycles.
That parking lot is planned to sit back 30 feet from W. Lawrence Avenue and to use permeable pavers and landscaping, with the resulting streetside space becoming a small public area featuring benches and planters along the avenue. The western portion of the site can't be built on at all, the report notes, because an MWRD easement for deep-tunnel sewer lines runs through that part of the property.
Cost, Contractor and Timeline
General contractor LG Group has topped out the structure, with the topping-out report valuing the project at $22.6 million. That figure differs from an earlier estimate in Chicago Construction News, which described the development as an $18 million project. The full building permit was issued in October 2025, and completion is slated for the first quarter of 2027, according to the same topping-out report — though, as with earlier benchmarks in this project's timeline, that date could still shift before the building opens its doors.