Elk Grove Village trustees this week approved a Cook County property-tax incentive application for a new three-building Stream Data Centers campus planned on 35 acres at 2000 Landmeier Road, a project officials say would not be financially viable without the tax break. The village board’s approval is not the final word, though — Cook County Board approval is still required before the incentive can take effect.
The project, reported by the Chicago Tribune, calls for a Cook County Class 6B incentive that would assess the property at 10% of market value for the first 10 years, stepping up to 15% in year 11 and 20% in year 12. Dallas-based Stream Data Centers is pitching the campus as a $588 million redevelopment, and company officials have said the project would not be economically feasible without the incentive, according to the same report.
Without an abatement, industrial properties in the village are assessed at 25% of market value, according to the Village of Elk Grove Village. The village notes it has supported more than 300 such industrial tax-abatement applications since the programs began in 1984, and that Class 6B eligibility generally requires an industrial use plus criteria like buying a long-vacant building or substantially renovating an existing one.
What the Finished Campus Would Pay — and Where It Sits Now
The property generated $609,000 in property taxes in 2022; the village annexed the site and awarded it industrial zoning entitlements in 2023, per the Tribune’s reporting. Once complete, the campus is projected to pay $15.4 million in annual property taxes during the incentive period — and an estimated $38.6 million once the 12-year break expires, the Tribune reports.
Village Manager Craig Johnson told the Tribune that the property will generate more tax revenue than it did before, even with the credit in place, adding that developments like this one have a significant impact and that the resulting tax benefits extend to the village, schools, parks and the library. Johnson also said Elk Grove Village uses Class 6B incentives frequently to encourage investment and keep projects in Cook County, going so far as to call the suburb the data center capital of the Midwest, according to the same report.
The Landmeier Road site was once home to the Roppolo residential subdivision, which dated to the 1950s. Stream made purchase offers to homeowners in 2023, with individual properties reportedly receiving roughly $950,000 each; fencing for demolition was reported in February 2024, per the Tribune.
A Big Build With a Timeline Still in Flux
As planned, the development includes three two-story buildings totaling 934,200 square feet of leasable space, with each building spanning 311,400 square feet, the Tribune reports. A ComEd substation serving the site broke ground about a year before the Tribune’s report, and the paper states the substation is expected to be powered on in 2028, with the first data center building scheduled to come online in 2029, the second in 2030 and the final building in 2031.
Not every account lines up on timing. Data Center Dynamics describes the same 260MW substation as expected to be ready for service in 2027 rather than 2028, and puts the planned campus at 1.2 million square feet across three buildings, with the first building expected to deliver 40MW of IT load. It is not clear from the available reporting whether the two timelines describe different construction milestones. Stream already operates two other data centers in Elk Grove Village, part of a cluster that, per the Tribune, now totals 20 data center sites in the village with five more under construction.
The Bigger Picture: Tax Breaks Add Up Across the Northwest Suburbs
Elk Grove Village’s embrace of data centers has made it a focal point of broader scrutiny. A Chicago Tribune and Illinois Answers Project analysis found that assessment reductions and incentives knocked nearly $2 billion off the taxable value of data centers across Elk Grove Village, Northlake and Franklin Park, amounting to almost $100 million in tax savings — including about $14.5 million saved by owners of five active Elk Grove Village data-center incentive complexes in 2025 alone, with the analysis estimating that reduction cut the average village homeowner’s property tax bill by roughly $33.
Other recent incentive deals show the trend isn’t limited to Stream. Aligned has also expressed interest in developing in the area, Data Center Dynamics reported.
The stakes extend beyond property tax rolls. Statewide, the Daily Herald notes that the Union of Concerned Scientists estimates data centers will drive 64% to 72% of Illinois’ electricity-demand growth between 2025 and 2030, and that DeKalb, Aurora and Elk Grove Village together account for half of the 34 Illinois data centers that have tapped the state’s data-center incentive program.
For now, the Stream proposal’s next stop is the Cook County Board, which must sign off before the incentive can take effect.