Greenfield Warehouse Developer Seeks Tax-Abatement Amendment After Missing 2025 DeadlineHancock County Council — Venue For Tax-Abatement Amendment
Google Street View

A Kansas City developer that built just one of three promised warehouses at a Greenfield business park is now asking Hancock County to amend its tax-abatement statement of benefits, reverting to the original schedule, to finish the job — with smaller buildings and a lower price tag than originally pitched. VanTrust Real Estate completed the 800,000-square-foot first building at Air 70 Logistics Park in 2023, but construction on the other two never started by the mid-2025 deadline written into its economic development agreements. Those agreements have since expired, but the original tax abatement approval remains in place.

Now VanTrust wants to build Building 2 at 523,000 square feet and Building 3 at 261,600 square feet, both scaled down from the 677,160 and 294,840 square feet proposed in late 2021, according to The Daily Reporter. The company plans to build both structures at the same time and expects them finished by the end of 2027. Air 70 Logistics Park sits near the intersection of County Roads 700 West and 400 North, close to Indianapolis Regional Airport and Interstate 70, and VanTrust describes the site on its own website as a 132-acre industrial park meant to eventually total 1.8 million square feet across three buildings.

A Shrinking Price Tag and a Missed Deadline

The numbers attached to the project have moved around depending on when they were reported. The Daily Reporter's new coverage says the proposed investment has fallen from an initial $115 million projection to $87.4 million. Those figures come from different points in time and show a project whose scope and cost have shifted since it was first approved.

VanTrust received a 10-year real property tax abatement for all three buildings back in October 2021, under a standard descending schedule that started at 100 percent in year one and dropped by 10 percentage points annually down to 10 percent in the final year. Hancock County commissioners then signed an economic development agreement at the start of 2022 with an amended abatement schedule — deductions of 100, 95, 90, 85, 80, 75, 70, 65, 60 and 55 percent over the term — with the extra payments meant to supplement taxes paid. That agreement required construction on all three buildings to begin no later than mid-2025. Only the first building had gone up by then, so per the same report, the agreements expired.

What's Leasing, What's Still Waiting

The first building isn't sitting empty. It's leased to both Neovia Logistics and Legacy Supply Chain, and VanTrust's development director, Brice Harrison, said Neovia employs 340 people on an annual basis while Legacy is aiming to employ 115. Legacy's footprint there is substantial — the company signed a lease for 430,881 square feet at the Owens Farm Court address, according to CoStar. Harrison told the Daily Reporter the remaining two sites have simply been waiting for the market to turn, saying it's time to build again.

The proposed new resolution, which the Hancock County Council is set to consider and vote on December 2, would restore the regular 10-year abatement schedule approved in late 2021 rather than the amended economic-development-agreement version. VanTrust projects Buildings 2 and 3 would generate $4.8 million in additional county tax revenue over the next decade.

A Warehouse Market That Finally Picked Up

The timing lines up with a broader turnaround in the local industrial market. The county's warehouse market has experienced an upturn over the past year-plus, with several previously vacant buildings along the Mt. Comfort Corridor either leased to new tenants or bought outright by previous owners, per the same article. That local trend tracks with wider regional numbers: Indianapolis industrial construction hit 8.9 million square feet across 24 projects in the third quarter of 2026, up 38.0 percent from the prior quarter, according to Cushman & Wakefield. Vacancy across the metro fell to 5.2 percent, its lowest mark since the third quarter of 2022, while net absorption reached 3.8 million square feet — the fifth straight quarter above 3.0 million. More than half of that construction pipeline, 54.0 percent, is speculative; 12.2 percent of speculative space is pre-leased.

Not Every Promised Building Gets Built

Air 70's stalled middle chapter isn't unique in Hancock County. Of 22 Buck Creek Township buildings tied to county economic development agreements, only four have actually been built, the Daily Reporter's review of county auditor data found. Just three buildings currently make economic-development-agreement payments to the auditor's office: Walmart's future IND6 facility, Air 70 Building 1, and 70 Connect III. Amazon, whose building sits at 2463 N. Buck Creek Road, had an EDA associated with it, though its leaders later said they did not want to participate and would simply pay taxes.

Hancock County Council member Keely Butrum raised concerns in the report, saying the council should have kept the original 10-year abatement schedule rather than entertaining the economic development agreement in the first place, and worrying that too many warehouses concentrated in one area could drag down rents and resale values. Council member Clark Smith argued the county's demographics are changing and that development should shift toward higher-skilled jobs rather than more warehouse space. Council member Kent Fisk said speculative warehouses remain a tainted prospect while so much existing supply sits unbuilt. The scale of what's already been promised elsewhere in the county is notable, too: a separate set of agreements covering Lauth Group's western Hancock County logistics developments totaled more than 4.1 million square feet and an estimated investment above $300 million, and a 2022 report pegged the combined economic development payments from the Lauth and VanTrust agreements at nearly $14.3 million over their ten-year spans.

Developers have continued to bring new requests for tax abatements on speculative warehouses before the Hancock County Council even as the Air 70 saga plays out, the Daily Reporter reported. Whatever the council decides on December 2, VanTrust's pitch marks an attempt to close out a project that, five years after it was first approved, remains two-thirds unbuilt.