Drivers on I-94 between Albertville and Monticello are now cruising on three full lanes in each direction after the Minnesota Department of Transportation finished a two-year, $76 million rebuild of the corridor. All six lanes initially opened to traffic in early November; on Nov. 19, MnDOT announced that westbound traffic was using the new permanent three-lane roadway.
The Minnesota Department of Transportation, the state agency responsible for planning, building and maintaining highways, bridges and transit systems, confirmed the milestone after construction that began in 2024. According to MnDOT, the agency completed the two-year, $76 million Corridors of Commerce-funded construction project, expanding the freeway to three lanes each way between the two Wright County communities.
The scope went well beyond adding pavement. As Wisevoter reported, the project included a rebuilt road surface, improved drainage infrastructure, a new westbound bridge over Wright County Road 19, a widened westbound bridge over County Road 75, and two noise walls near Monticello. MnDOT's project page confirms the agency replaced the westbound bridge over Wright Co. Rd. 19 in Albertville and widened the westbound bridge over Co. Rd. 75 in Monticello.
A Staged Rollout Before the Full Opening
A Staged Rollout Before the Full Opening All six lanes initially opened in early November, according to HometownSource. MnDOT's Nov. 19 announcement marked westbound traffic moving onto the new permanent three-lane roadway.
Drivers shouldn't assume construction crews are entirely gone, either. MnDOT cautioned that occasional single-lane closures may still occur as crews finish final project items, according to a report from HometownSource. No timeline for those closures has been specified.
Old Lanes Get New Life as a Pavement Lab
Rather than letting the former westbound lanes go to waste, MnDOT plans to hand them over to MnROAD, the agency's pavement research program. MnROAD will use the former westbound I-94 lanes to study how pavement performs under heavy truck traffic, per the agency's project materials. Signs and gates are planned to direct trucks onto the test section and back onto the interstate, turning a stretch of retired highway into a long-term research tool for engineers studying how heavy loads wear down road surfaces over time.
More Wright County Work Planned for 2027
The Albertville-to-Monticello job isn't the last word on I-94 upgrades in the area. MnDOT has additional work planned in Wright County for 2027, including a resurfacing and update of the Highway 25 interchange bridge over I-94 in Monticello. The planned update is at the Highway 25 bridge over I-94 in Monticello.
Further west, MnDOT is also planning to reconstruct the Highway 24 interchange at I-94 in Clearwater during 2026-2027. That project is expected to include a new bridge, ramp accesses with roundabouts, sidewalks and a multi-use trail, according to the agency. Together, the Monticello and Clearwater projects suggest the broader I-94 corridor in Wright County will keep seeing construction activity even after this latest expansion wraps up.