Quantcast

Another 10-day Muni T-Third line bus substitution kicks off this weekend

Photo: Teresa Hammerl/Hoodline
By Teresa Hammerl - Published on July 25, 2019.

This Saturday, July 27, Muni's T-Third rail line is shutting down for yet another round of bus substitutions between Embarcadero station and Sunnydale.

The substitutions, which will last approximately 10 days, are the third on the line this year. The T-Third also underwent a two-month bus substitution in January and a 10-day interruption at the end of May. 

The line has been in upheaval this year, as Muni demolishes and replaces the platforms at the UCSF Mission Bay station to accommodate the forthcoming Chase Center. The Chase Center, which will be the new home of the NBA's Golden State Warriors, will open in September. 

At the end of the last shutdown, SFMTA spokesperson Erica Kato said the line would only need to be closed to trains for one more weekend. Asked why the effort is now extending from two days to 10, Kato said it’s to perform work and testing around the clock, uninterrupted by train service.

The T-Third project was originally set to be completed by late April. Kato said the extension was caused by weather delays, "due to all the rain during construction earlier this year."

Currently, crews are wrapping up pouring concrete at two intricate rail sections, both the single and double crossovers, Kato tells us. During the bus substitution, final concrete pouring will be combined with additional equipment testing.

Muni stations between the Embarcadero and the terminal at Bayshore Boulevard and Sunnydale Avenue will be closed. During that time, buses will service all stops along Third Street, curbside.

Customers traveling underground towards Sunnydale will have to transfer to a T-Third bus at Embarcadero station. Signs will direct riders to the shuttles.

The E-Embarcadero will also go offline; customers can use the F-Market line as an alternative. On Third Street, one travel lane in each direction will remain open near the construction site throughout this project phase.

When the UCSF Mission Bay station reopens, it will have one 320-foot platform that can hold up to 700 travelers at one time, allowing four two-car trains to stop simultaneously for events at the Chase Center.

The new platform is currently anticipated to open in August, but no opening date has been set yet, officials said.

About 12 hours ago
San Francisco Castro Duboce Triangle

Castro Muni station elevator project delayed, Harvey Milk Plaza redesign slowly moves forward

Hoodline has learned that the construction of a new glass elevator at Castro Muni station and Harvey Milk Plaza (Market and Castro Streets) has been delayed until fall 2021. Read More

Nov 20, 2020
San Francisco

SF is hiring artists and performs to do COVID-19 PSAs

Work will be slightly less scarce for 30 underemployed artists and performers in the coronavirus economy, as a new San Francisco Creative Corps will be giving the gift of gigs. Read More

Nov 20, 2020
San Francisco Mission

Mozzeria, the Mission's Deaf-owned pizzeria, has closed after nine years

The Bay Area has lost its only Deaf-owned and operated restaurant, Mozzeria (3228 16th St.), due to the ongoing pandemic downturn. Deaf owners Melody and Russ Stein say they will continue operating their food truck, but the time has come to give up the brick-and-mortar restaurant in the Mission. Read More

Nov 20, 2020
San Francisco Castro Mission

Notorious Castro drug den sells for $4.8 million after complete renovation

After undergoing a complete renovation, a notorious Castro neighborhood building at 517-519 Sanchez Street (near 18th Street) has sold for $4.8 million. Read More